Nepal Complete Stalled National Pride Projects (2 Years) Progress 2026
रोकिएका राष्ट्रिय गौरवका आयोजना सम्पन्न (२ वर्ष)
Overall Progress
10%
Status
Stalled
रोकिएको
6
Evidence Items
0
Sources
5
Linked Projects
verified
Trust Level
About This Commitment
Key stalled projects: Fast Track at 45.16% (Rs 83B of Rs 212B spent, deadline Apr 2027, Khokana dispute blocking start point). Budhigandaki Hydropower and Nijgadh Airport spent Rs 0 in first 6 months of FY 2025/26. Railway at 5% since 2008. Melamchi halted by protests Jan 2026. Only 15.49% of national pride budget spent in H1. World Bank says 41 years needed at current pace. PM Oli May 2024 directive for review yielded no visible results.
सरकार गठनको २ वर्षभित्र सबै रोकिएका राष्ट्रिय गौरवका आयोजना लेखापरीक्षण र सम्पन्न
Budget
NPR 50.0 Crore
Spent: NPR 10.4 Crore (21%)
Track Live Updates
See real-time signals, community evidence, and AI-powered briefings on this commitment.
View Live TrackerMore Infrastructure Commitments
Data sourced from RSP "बाचा पत्र 2082" (Citizen Contract) — 100 Pillars of Policy Departure. Last updated: 2026-03-25. How we track commitments · Live tracker