Nepal Complete All National Pride Projects in 2 Years Progress 2026

२ वर्षमा सबै राष्ट्रिय गौरवका आयोजना सम्पन्न

Overall Progress

8%

Status

Stalled

रोकिएको

Deadline: April 1, 2028

6

Evidence Items

0

Sources

4

Linked Projects

verified

Trust Level

About This Commitment

27 national pride projects total; only 4 completed (Upper Tamakoshi 456 MW, Gautam Buddha Airport, Pokhara Airport, Melamchi Phase 1). World Bank warns remaining 17 would take 41 more years at current pace. FY 2025/26 budget: Rs 67.08B allocated, only 15.49% (Rs 10.39B) spent in first 6 months. Fast Track at 45% progress. Budhigandaki and Nijgadh spent zero. Railway project at 5% since 2008.

सरकार गठनको २ वर्षभित्र सबै तोकिएका राष्ट्रिय गौरवका आयोजना सम्पन्न गर्ने

Budget

NPR 50.0 Crore

Spent: NPR 10.4 Crore (21%)

Track Live Updates

See real-time signals, community evidence, and AI-powered briefings on this commitment.

View Live Tracker

More Infrastructure Commitments

Data sourced from RSP "बाचा पत्र 2082" (Citizen Contract) — 100 Pillars of Policy Departure. Last updated: 2026-03-25. How we track commitments · Live tracker