Nepal East-West Electric Railway Progress 2026
पूर्व-पश्चिम विद्युतीय रेलमार्ग
Overall Progress
5%
Status
Stalled
रोकिएको
4
Evidence Items
0
Sources
2
Linked Projects
verified
Trust Level
About This Commitment
945 km Kakarbhitta-Kanchanpur railway. DPRs completed for Bardibas-Simara (108 km), Simara-Tansariya (127 km), Tansariya-Butwal (64 km). Only physical work: Bardibas-Nijgadh 70 km section with ~50 km track bedding done. Rs 11.22B spent total, Rs 4B/year allocation. 2025 development: government considering rerouting entire line along East-West Highway to avoid land compensation — would require new DPR and abandon 15+ years of planning. National pride project with 5% progress since 2008. Est. cost $3B.
यात्रु र मालवस्तु ढुवानीका लागि पूर्व-पश्चिम विद्युतीय रेलमार्ग निर्माण
Budget
NPR 100.0 Crore
Spent: NPR 11.2 Crore (11%)
Geographic Scope
Track Live Updates
See real-time signals, community evidence, and AI-powered briefings on this commitment.
View Live TrackerMore Transport Commitments
Data sourced from RSP "बाचा पत्र 2082" (Citizen Contract) — 100 Pillars of Policy Departure. Last updated: 2026-03-25. How we track commitments · Live tracker