Nepal East-West Highway 4-Lane Expansion Progress 2026
पूर्व-पश्चिम राजमार्ग ४ लेन विस्तार
Overall Progress
18%
Status
In Progress
प्रगतिमा
5
Evidence Items
0
Sources
4
Linked Projects
verified
Trust Level
About This Commitment
1,028 km highway from Kakarbhitta to Kanchanpur. Multiple sections under work: Kamala-Kanchanpur (Siraha/Saptari) at 67% but behind deadline; Narayanghat-Butwal 6-lane upgrade at 42% by Chinese contractor; Kakarbhitta-Laukahi 120 km with ADB $300M loan tendered; Koshi Province upgrade to Asian Highway standards underway. No work started in Sudurpashchim Province. Electricity pole relocation, land acquisition delays across sections.
सम्पूर्ण पूर्व-पश्चिम राजमार्ग (महेन्द्र राजमार्ग) लाई ४ लेन विभाजित राजमार्गमा स्तरोन्नति
Budget
NPR 20.0 Crore
Source: ADB ($300M loan), World Bank ($450M loan), Government of Nepal
Geographic Scope
Track Live Updates
See real-time signals, community evidence, and AI-powered briefings on this commitment.
View Live TrackerMore Transport Commitments
Data sourced from RSP "बाचा पत्र 2082" (Citizen Contract) — 100 Pillars of Policy Departure. Last updated: 2026-03-25. How we track commitments · Live tracker